[53191] in Hotline Meeting
Shutdown request for building 8 on 12/27
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Dec 19 13:55:55 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451C54F70@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andreab@MIT.EDU, C-Zone <C-Zone@MIT.EDU>, carolr@MIT.EDU,
Cust-Coach
<cust-coach@MIT.EDU>, cwyckoff@MIT.EDU, glabonte@MIT.EDU,
kmartel@MIT.EDU, lechtman@MIT.EDU, schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 19 Dec 2000 13:55:43 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; C-Zone; carolr@mit.edu; Cust-Coach;
> cwyckoff@mit.edu; glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 8 on 12/27
>
>
The following shutdown request is for builidng 8 on 12/27. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Critical
> Building: 8
> Date: 12/27/00
> Day: Wednesday
> Time: 6 am - 9 am
> System: Domestic and lab processed water
> Duration: 3 hours
> Reason:
> Tie in the new safety showers.
>
> Effect:
> There will be no hot or cold domestic or lab processed water during this
> time.
>
>