[53187] in Hotline Meeting
Shutdown request for building 18 on 12/27
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Dec 19 08:04:03 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451C54ED1@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, akelsey@MIT.Edu,
Cust-Coach
<cust-coach@MIT.Edu>, mbj@MIT.Edu, rjwilk@MIT.Edu,
schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 19 Dec 2000 08:03:51 -0500
Return-Receipt-To: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 18 on 12/27
>
>
The following shutdown request is for building 18 on 12/27. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintnenance
> Status: Critical
> Building: 18
> Date: 12/27/00
> Day: Wednesday
> Time: 8 am - 5 pm
> System: Fire Protection will affect the yard loop as well as the building
> Duration: 9 hours
> Reason:
> Tie in new standpipe in north stairwell into supply main.
>
> Effect:
> There will be a loss of fire protection water during this time.
>
>