Building 68 shutdown request for 1/17/01

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Dec 18 09:32:46 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451C54DD1@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>, jfucillo@MIT.EDU,
        jmganno@MIT.EDU, maureen@MIT.EDU, rberlin@MIT.EDU, shyoung@MIT.EDU,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Mon, 18 Dec 2000 09:32:38 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; jfucillo@mit.edu; jmganno@mit.edu;
> maureen@mit.edu; rberlin@mit.edu; shyoung@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 68 shutdown request for 1/17/01
> 
> 
The following shutdown request for building 68 on 1/17/01.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
2-1599

> Status: Normal
> Building: 68
> Date: 1/17/01
> Day: Wednesday
> Time: 8:30 am - 12:30 pm
> System: AH1, AH2, AH3, & AH7
> Duration: 4 Hours
> Reason: 
> Filter changes.
> 
> 
> Effect: 
> There will be a loss of supply ventilation, supply cooling, suppply
> heating, exhaust laboratory air and and general exhaust air.
> 
> 