[53126] in Hotline Meeting
W7 Shutdown request for building W7 on 12/15
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 14 11:11:21 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451C54BC6@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: kcn@MIT.EDU, mwhelan@MIT.EDU, rberlin@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 14 Dec 2000 11:11:14 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: kcn@mit.edu; mwhelan@mit.edu; rberlin@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: W7 Shutdown request for building W7 on 12/15
>
>
The following shutdown request is for building W7 on 12/15. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: W7- Baker Housr
> Date: 12/15/00
> Day: Friday
> Time: 7 am - 3 pm
> System: Fire Protection Water
> Duration: 8 hours
> Reason:
> New tie in of water service.
>
> Effect:
> There will be no fire protection water during this time.
>
>