Building 39 Shutdown request for 12/28/00

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Dec 13 14:03:43 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451C54B0E@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
        mcgrath@mtl.mit.edu, rcf@space.mit.edu, walsh@mtl.mit.edu,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 13 Dec 2000 14:03:21 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 39 Shutdown request for 12/28/00
> 
> 
The following shutdown request is for building 39 on 12/28/00.  Please let
me know if this does or does not meet witb your approval.

Thank you
Dawn Simonelli
2-1599

> Status: Normal
> Building: 39 entire building
> Date: 12/28/00
> Day: Thursday
> Time: 8 am - 12 noon
> System: Lab Vacuum
> Duration: 4 hours
> Reason: 
> Maintenance as per  manufacture's specifications.
> 
> Effect: 
> There will be no lab vacuum air during this time.
> 
> 