[53103] in Hotline Meeting
Re: Building 36 shutdown request for 12/21
daemon@ATHENA.MIT.EDU (Peter Bedrosian)
Tue Dec 12 10:47:06 2000
Message-Id: <3.0.2.32.20001212105119.01210950@po12.mit.edu>
Date: Tue, 12 Dec 2000 10:51:19 -0500
To: Dawn Simonelli <dsimone@PLANT.MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
Cust-Coach <cust-coach@MIT.EDU>, gfp170@rle.mit.edu, schedule@MIT.EDU,
shutdowns@MIT.EDU
From: Peter Bedrosian <peterb@MIT.EDU>
Cc: shutdown@PLANT.MIT.EDU
In-Reply-To: <82F0D564C5ADD31180EF00508B556451C5486F@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
This is OK with the Schedules Office.
At 11:00 AM 12/11/2000 -0500, Dawn Simonelli wrote:
>> To: B-Zone; Cust-Coach; gfp170@rle.mit.edu; schedule@mit.edu;
>> shutdowns@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: Building 36 shutdown request for 12/21
>>
>>
>The following shutdown request is for building 36 on 12/21. Please let me
>know if this does or does not meet with your approval.
>
>Thank you
>Dawn Simonelli
>2-1599
>
>
>> Status: Normal
>> Building: 36
>> Date: 12/21/00
>> Day: Thursday
>> Time: 6 am - 10 am
>> System: Domestic Water
>> Duration: 4 hours
>> Reason:
>> To replace a valve for new domestic water pumps.
>>
>> Effect:
>> There will be no hot and cold domestic water. Also no hot or cold lab
>> processed water.
>>
>>
>