[53089] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Building 36 shutdown request for 12/21

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Dec 11 11:04:22 2000

Message-ID: <82F0D564C5ADD31180EF00508B556451C5486F@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        gfp170@rle.mit.edu, schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 11 Dec 2000 11:00:01 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; gfp170@rle.mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 36 shutdown request for 12/21
> 
> 
The following shutdown request is for building 36 on 12/21.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
2-1599


> Status: Normal
> Building: 36
> Date: 12/21/00
> Day: Thursday
> Time: 6 am - 10 am
> System: Domestic Water
> Duration: 4 hours
> Reason: 
> To replace a valve for new domestic water pumps.
> 
> Effect: 
> There will be no hot and cold domestic water.  Also no hot or cold lab
> processed water.
> 
> 