[53075] in Hotline Meeting
Re: W34 Shutdown request for 12/15
daemon@ATHENA.MIT.EDU (Daniel J. Martin)
Fri Dec 8 09:11:18 2000
Message-Id: <3.0.2.32.20001208091528.01b78098@hesiod>
Date: Fri, 08 Dec 2000 09:15:28 -0500
To: Dawn Simonelli <dsimone@PLANT.MIT.EDU>, clroyer@MIT.EDU,
D-Zone <D-Zone@MIT.EDU>, jaheiney@MIT.EDU, slett@MIT.EDU,
schedule@MIT.EDU, shutdowns@MIT.EDU
From: "Daniel J. Martin" <djmartin@MIT.EDU>
Cc: shutdown@PLANT.MIT.EDU, nmagnuso@MIT.EDU, bwc@MIT.EDU
In-Reply-To: <82F0D564C5ADD31180EF00508B556451C54700@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Dawn,
Ok Athletics.
Go Tech!
At 08:03 AM 12/08/2000 -0500, Dawn Simonelli wrote:
>> To: clroyer@mit.edu; D-Zone; djmartin@mit.edu; jaheiney@mit.edu;
>> slett@mit.edu; schedule@mit.edu; shutdowns@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: W34 Shutdown request for 12/15
>>
>>
>The following shutdown request is for building W34 on 12/15 Please let me
>know if this does or does not meet with your approval.
>
>Thank you
>Dawn Simonelli
>2-1599
>
>> Status: Critical
>> Building: W34
>> Date: 12/15/00
>> Day: Friday
>> Time: 10 am - 2 pm
>> System: All steam, DHW for showers, heat, zamboni and hot water
>> Duration: 4 hours
>> Reason:
>> To tie in the new steam supply.
>>
>>
>> Effect:
>> There will be a loss of hot domestic and heating hot water. There will
>> be no supply heatig or high, medium or low steam pressure. Also no smoke
>> detectors.
>>
>>
>
Daniel J. Martin MIT Box 397494
Assistant Department Head Cambridge, MA 02139-7404
For Facilities and Operations Phone: (617)253-5003
Department of Athletics Fax: (617)258-7343
E-Mail: DJMARTIN@MIT.EDU