Building 6 shutdown request for 12/12 & 13
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 7 14:50:37 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451C546A0@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: akelsey@MIT.EDU, andreab@MIT.EDU, C-Zone <C-Zone@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>, cwyckoff@MIT.EDU, doreenc@MIT.EDU,
glabonte@MIT.EDU, mbj@MIT.EDU, mhankin@MIT.EDU, naylor@MIT.EDU,
radams@MIT.EDU, rjwilk@MIT.EDU, rrdasari@MIT.EDU, saraf@MIT.EDU,
schedule@MIT.EDU, tiki@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 7 Dec 2000 14:46:18 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: akelsey@mit.edu; andreab@mit.edu; C-Zone; Cust-Coach;
> cwyckoff@mit.edu; doreenc@mit.edu; glabonte@mit.edu; mbj@mit.edu;
> mhankin@mit.edu; naylor@mit.edu; radams@mit.edu; rjwilk@mit.edu;
> rrdasari@mit.edu; saraf@mit.edu; schedule@mit.edu; tiki@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Building 6 shutdown request for 12/12 & 13
>
>
the following shutdown request is for building 6 on 12/12-13th. Please let
me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: 6
> Date: 12/12/00
> Day: Tuesday
> Time: 7:30 am - 2:30 pm
> System: Fire Alarm
> Duration: 7 hours
> Reason:
> Tie in new system fire alarm charge sprinkler lines in penthouse,
>
> Effect:
> There will be no fire alarm or fire protection water
>
>