Rescheduled shutdown for W7

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 7 12:54:00 2000

Message-ID: <82F0D564C5ADD31180EF00508B556451C54677@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: kcn@mit.edu, mwhelan@mit.edu, rberlin@mit.edu, shutdowns@mit.edu,
        schedule@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 7 Dec 2000 12:49:45 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	kcn@mit.edu; mwhelan@mit.edu; rberlin@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Rescheduled shutdown for W7
> 
> 
The following shutdown is being rescheduled for building W7.  They would
like to have it changed to the 11th if possible.  Please let me know if this
does or does not meet with your approval.

Thank you 
Dawn Simonelli	
2-1599

> Status: Normal
> Building: W7
> Date: 12/11/00
> Day: Monday
> Time: 9 AM - 5 PM
> System: Fire Protection Water
> Duration: 8 hours
> Reason: 
> To  tie in new fire protection loop service for west campus.
> 
> Effect: 
> There will not be any fire protection water during this time.
> 
> 