W7 Shutdown request for 12/8/00
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Dec 6 13:11:37 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451C54552@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.EDU>, kcn@MIT.EDU, mwhelan@MIT.EDU, rberlin@MIT.EDU,
schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 6 Dec 2000 13:07:18 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: D-Zone; kcn@mit.edu; mwhelan@mit.edu; rberlin@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: W7 Shutdown request for 12/8/00
>
>
The following shutdown request is for W7 on 12/8/00. Please let me know if
this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: W07
> Date: 12/8/00
> Day: Friday
> Time: 9 am - 5 pm
> System: Fire protection water
> Duration: 8 hour
> Reason:
> To tie in new fire protection loop service for west campus.
>
>
> Effect:
> There will be no fire protection water during this time.
>
>