[53020] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown request for building 39 on 12/9

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Dec 4 12:32:08 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451C5406A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
        mcgrath@mtl.mit.edu, rcf@space.mit.edu, walsh@mtl.mit.edu,
        shutdowns@MIT.EDU, schedule@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Mon, 4 Dec 2000 12:27:46 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 39 on 12/9
> 
> 
The following shutdown request is for building 39 on 12/9/00.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
2-1599

> Status: Normal
> Building: 39 Entire building
> Date: 12/9/00
> Day: Saturday
> Time: 7 am to 3 pm
> System: AH 1, 2, & 3
> Duration: 8 Hours
> Reason: 
> To clean the air plenum.
> 
> Effect: 
> There will be no supply ventilation, cooling or heating.
> 
> 

home help back first fref pref prev next nref lref last post