[53008] in Hotline Meeting
Building E25-044 Shutdown request for 12/7/00 and 12/14/00
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Dec 1 10:57:00 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451B71FFC@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andrea@psyche.mit.edu, andreab@MIT.EDU, arolle@MIT.EDU, bengel@MIT.EDU,
cpoon@MIT.EDU, E-Zone <E-Zone@MIT.EDU>, elworthi@MIT.EDU,
hegarty@MIT.EDU, jmganno@MIT.EDU, jrauch@MIT.EDU, loudib@MIT.EDU,
rfink@MIT.EDU, roge@med.mit.edu, schedule@MIT.EDU, sdl-adm-lib@MIT.EDU,
shyoung@MIT.EDU, schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 1 Dec 2000 10:52:40 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: andrea@psyche.mit.edu; andreab@mit.edu; arolle@mit.edu;
> bengel@mit.edu; cpoon@mit.edu; E-Zone; elworthi@mit.edu; hegarty@mit.edu;
> jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu; rfink@mit.edu;
> roge@med.mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu; shyoung@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Building E25-044 Shutdown request for 12/7/00 and 12/14/00
>
>
The following shutdown request is for building E25-044 on 12/7/00 and
12/14/00. Please let me know if this does or does not meet with your
approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: E25 -044
> Date: 12/7/00
> Day: Thursday
> Time: 7:30 am - 3:30 pm each day
> System: Fire Protection Water
> Duration: 8 hours
> Reason:
> Removing and Replacing ceiling tiles.
>
> Effect:
> There will be no fire protection water.
>
>