Buildung 54 Shutdown request for 12/6/00
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Dec 1 10:32:05 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451B71FE6@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, kvkeefe@MIT.Edu,
politano@MIT.Edu, schedule@MIT.Edu, sdl-adm-lib@MIT.Edu,
w1mx-officers@MIT.Edu, wendell@MIT.Edu, schedule@MIT.Edu,
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 1 Dec 2000 10:27:42 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; kvkeefe@mit.edu; politano@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; w1mx-officers@mit.edu;
> wendell@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Buildung 54 Shutdown request for 12/6/00
>
>
The following shutdown request is for builidng 54 rooms 1227,1221 and 1319
on 12/6. Please let me kniw if this does or does not meet with your
approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: 54
> Date: 12/6/00
> Day: Wednesday
> Time: 7:30 am - 12:00 Noon
> System: Exhaust air
> Duration: 4 1/2 hours
> Reason:
> To change the sheaves on the fans and motors.
>
>
> Effect:
> There will be no exhaust-labortory air.
>
>