Bldg. 36 - 252 - 12/5 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 28 12:04:02 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451BD1F31@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gfp170@rle.mit.edu'" <gfp170@rle.mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 28 Nov 2000 11:59:59 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	gfp170@rle.mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 36 - 252 - 12/5 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Bldg. 36 - 252 (and rest of
2nd floor) on Tuesday, 12/5 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 36-252
> Date: 12/5/00
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Chilled Water
> Duration: 8 hours
> Reason: 
> Tie in new lines.
> 
> Effect: 
> Loss of chilled water (air conditioning) in 36-252 and restof 2nd floor
> during the shutdown period./
> 
> 