Bldg. 66 - 519 and 521 - 11/14 - Cold Lab Process Water Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 9 12:06:51 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511055E4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'ccooney@mit.edu'"
	 <ccooney@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        "'patsys@mit.edu'" <patsys@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'swetzel@mit.edu'" <swetzel@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 9 Nov 2000 12:03:18 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	shutdowns@mit.edu; ccooney@mit.edu; cust-coach@mit.edu;
> patsys@mit.edu; schedule@mit.edu; swetzel@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - 519 and 521 - 11/14 - Cold Lab Process Water
> Shutdown Request
> 
> 
The following Cold Lab Process Water shutdown request for Bldg. 66 - 519 and
521 on Tuesday, 11/14 is for your review and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 66 - 519 and 521
> Date: 11/14/00
> Day: Tuesday
> Time: 8 AM - 12 Noon
> System: Cold Lab Process Water
> Duration: 4 hours
> Reason: 
> Install control valve on primary feed side of heat exchanger.
> 
> Effect: 
> Loss of cold lab process water in 66-519 and 521. This means there will be
> no cold lab process water for any lab equipment requiring this to make it
> operational.
> 
> 