Bldg. E52 - North East Side - 11/8 - Critical Supply Ventilation

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 7 13:49:10 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511055C6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
        "'lhill@mit.edu'" <lhill@MIT.EDU>,
        "'lmorales@mit.edu'"
	 <lmorales@MIT.EDU>,
        "'lreinher@mit.edu'" <lreinher@MIT.EDU>,
        "'maureen@mit.edu'" <maureen@MIT.EDU>,
        "'mscoppa@mit.edu'"
	 <mscoppa@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
        "'rberlin@mit.edu'"
	 <rberlin@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'sdimond@mit.edu'" <sdimond@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 7 Nov 2000 13:45:38 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	andreab@mit.edu; gwj@mit.edu; lhill@mit.edu; lmorales@mit.edu;
> lreinher@mit.edu; maureen@mit.edu; mscoppa@mit.edu; mwf@mit.edu;
> rberlin@mit.edu; schedule@mit.edu; sdimond@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E52 - North East Side - 11/8 - Critical Supply
> Ventilation Shutdown Request
> 
> 
The following shutdown request for Bldg. E52 - Northeast side of building on
Wednesday, 11/8 is for your review and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: E52 - Northeast Side
> Date: 11/8/00
> Day: Wednesday
> Time: 7:30 AM - 9:30 AM
> System: Supply Fan 2 (supply ventilation)
> Duration: 2 hours
> Reason: 
> Change speed of motor.
> 
> Effect: 
> Loss of supply ventilation (fresh air from outside) in the northeast side
> of E52 during the 2-hour shutdown period.
> 
> 