Bldg. 26 104,106, 111, 112, 410, 502 and 506 - 11/7 - Critical Sh

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 6 08:40:30 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511055AB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@MIT.EDU>,
        "'b-zone@mit.edu'"
	 <b-zone@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        "'dudley@mit.edu'" <dudley@MIT.EDU>,
        "'gfp170@rle.mit.edu'"
	 <gfp170@rle.mit.edu>,
        "'kates@mit.edu'" <kates@MIT.EDU>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.EDU>, "'lsc@mit.edu'" <lsc@MIT.EDU>,
        "'mhankin@mit.edu'" <mhankin@MIT.EDU>,
        "'nsteele@mit.edu'"
	 <nsteele@MIT.EDU>,
        "'radams@mit.edu'" <radams@MIT.EDU>,
        "'safety@mit.edu'" <safety@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 6 Nov 2000 08:36:59 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	andreab@mit.edu; b-zone@mit.edu; cust-coach@mit.edu; dudley@mit.edu;
> gfp170@rle.mit.edu; kates@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; radams@mit.edu; safety@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 104,106, 111, 112, 410, 502 and 506 - 11/7 -
> Critical Shutdown Request
> 
> 
The following Critical shutdown request for Bldg. 26 - 104, 106, 111, 112,
410, 502 and 5206 on Tuesday, 11/7 is for your review and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Operations Center
8-7872



> Status: Critical
> Building: 26- 104,106, 111, 112, 410, 502 and 506 
> Date: 11/7/00
> Day: Tuesday
> Time: 7 AM - 3 to 5 PM
> System: Hot and cold domestic and lab process water
> Duration: 8-10 hours
> Reason: 
> To repipe sewage discharge from this area of building to manhole structure
> in yard area.
> 
> Effect: 
> Loss of hot and cold domestic water in 104 (kitchen), 111(Ladies room),
> 112(Men's room), 106 (Janitor's Closet), 410 (Kitchen), Labs 502 and 506
> (also loss of hot and cold lab process water in these labs). Emergency
> showers and eyewashes in the labs will also not be operational during this
> 8-10 hour shutdown period.
> 
> 