[52638] in Hotline Meeting
Bldgs. E23 and E25 - 12/4 - Critical All Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 31 14:54:07 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451105572@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dwye@med.mit.edu'" <dwye@med.mit.edu>,
"'edwa@med.mit.edu'"
<edwa@med.mit.edu>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'andreab@mit.edu'"
<andreab@MIT.EDU>,
"'arolle@mit.edu'" <arolle@MIT.EDU>,
"'bengel@mit.edu'" <bengel@MIT.EDU>, "'cpoon@mit.edu'" <cpoon@MIT.EDU>,
"'e-zone@mit.edu'" <e-zone@MIT.EDU>,
"'elworthi@mit.edu'"
<elworthi@MIT.EDU>,
"'hegarty@mit.edu'" <hegarty@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'jrauch@mit.edu'"
<jrauch@MIT.EDU>,
"'loudib@mit.edu'" <loudib@MIT.EDU>,
"'rfink@mit.edu'"
<rfink@MIT.EDU>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 31 Oct 2000 14:50:37 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: dwye@med.mit.edu; edwa@med.mit.edu; roge@med.mit.edu;
> andrea@psyche.mit.edu; andreab@mit.edu; arolle@mit.edu; bengel@mit.edu;
> cpoon@mit.edu; e-zone@mit.edu; elworthi@mit.edu; hegarty@mit.edu;
> jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu; rfink@mit.edu;
> roge@med.mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> shutdowns@mit.edu; shyoung@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. E23 and E25 - 12/4 - Critical All Water Shutdown
> Request
>
>
The following Critical all water shutdown request for Bldgs.E23 and E25 for
Saturday, 12/4 is for your information and comment. Would you please let me
know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E23 and E25
> Date: 11/4/00
> Day: Saturday
> Time: 12 AM - 4 PM
> System: Hot and cold domestic and lab process water
> Duration: 4 hours
> Reason:
> To install isolation valves on the domestic water mains to separate E25
> from E23.
>
> Effect:
> Loss of hot and cold domestic and lab process water. This means that no
> toilets, showers, bathroom, kitchen faucets, emergency showers, drinking
> fountains or equipment requiring lab process water will be operational
> during the 4-hour shutdown period.
>
>