Bldg. E25 - 11/6 - Southwest Labs - Floors 2 thru 6 Shutdown Requ
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 31 13:18:20 2000
Message-Id: <82F0D564C5ADD31180EF00508B55645110556B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'andreab@mit.edu'"
<andreab@MIT.EDU>,
"'arolle@mit.edu'" <arolle@MIT.EDU>,
"'bengel@mit.edu'" <bengel@MIT.EDU>, "'cpoon@mit.edu'" <cpoon@MIT.EDU>,
"'e-zone@mit.edu'" <e-zone@MIT.EDU>,
"'elworthi@mit.edu'"
<elworthi@MIT.EDU>,
"'hegarty@mit.edu'" <hegarty@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'jrauch@mit.edu'"
<jrauch@MIT.EDU>,
"'loudib@mit.edu'" <loudib@MIT.EDU>,
"'rfink@mit.edu'"
<rfink@MIT.EDU>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 31 Oct 2000 13:14:54 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: andrea@psyche.mit.edu; andreab@mit.edu; arolle@mit.edu;
> bengel@mit.edu; cpoon@mit.edu; e-zone@mit.edu; elworthi@mit.edu;
> hegarty@mit.edu; jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu;
> rfink@mit.edu; roge@med.mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> shutdowns@mit.edu; shyoung@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E25 - 11/6 - Southwest Labs - Floors 2 thru 6 Shutdown
> Request
>
>
The following shutdown request for Bldg. E25 - Southwest Labs on Floors 2
thru 6 on Monday, 11/6 is for our information and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E25
> Date: 11/6/00
> Day: Monday
> Time: 7 AM - 3 PM
> System: Air Handler 6 (supply ventilation)
> Duration: 8 hours
> Reason:
> Installation of supply air bypass duct.
>
> Effect:
> Loss of supply ventilation in Bldg. E25 - Southwest Labs - floors 2 thru 6
> during the shutdown period.
>
>