[52606] in Hotline Meeting
Bldg. 35 - 11/4 - Building Electrical Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 30 07:42:07 2000
Message-ID: <82F0D564C5ADD31180EF00508B55645110554F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'b-zone@mit.edu'" <b-zone@MIT.Edu>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.Edu>,
"'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'emcmill@mit.edu'" <emcmill@MIT.Edu>,
"'gallant@mit.edu'"
<gallant@MIT.Edu>,
"'gerwent@mit.edu'" <gerwent@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'stiffler@mit.edu'"
<stiffler@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
Howard Harrison
<HHarriso@PLANT.MIT.EDU>
Date: Mon, 30 Oct 2000 07:38:39 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: b-zone@mit.edu; cust-coach@mit.edu; opsnote@mit.edu;
> emcmill@mit.edu; gallant@mit.edu; gerwent@mit.edu; schedule@mit.edu;
> stiffler@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; Howard Harrison
> Subject: Bldg. 35 - 11/4 - Building Electrical Power Shutdown Request
>
>
The following building electrical power rescheduled shutdown request for
Bldg. 35 now on Saturday, 11/4 is for your review and comment. This work was
initially scheduled for 10/7. Would you please let me know whether this
does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35
> Date: 11/4/00
> Day: Saturday
> Time: 6 AM - 10 PM
> System: Building Electrical Power
> Duration: 16 hours
> Reason:
> Transfer building 35 electrical power over to new substation in building
> 33.
>
> Effect:
> Loss of building power, access controls, computers, telephones,lighting
> (corridors, stairs), supply ventilation, fire alarm and exhaust hood air.
>
>