Bldg. 48 - 10/28 - 30 Rescheduled All Steam Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 27 07:45:59 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451105545@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'b-zone@mit.edu'" <b-zone@MIT.EDU>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.EDU>,
"'mistetri@mit.edu'" <mistetri@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sfrankel@mit.edu'"
<sfrankel@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 27 Oct 2000 07:42:42 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: b-zone@mit.edu; cust-coach@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 48 - 10/28 - 30 Rescheduled All Steam Shutdown Request
>
>
Dear Everyone:
I have just been informed that the All Steam shutdown which was scheduled
and approved for 10/21 to 10/23 did not occur. Would you please let me know
if it would be possible to schedule this work for tomorrow, Saturday, 10/28
up to Monday, 10/30 AM.
Thanks for your time and I look forward to hearing from you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 48
> Date: 10/28/30
> Day: Saturday
> Time: 7 AM (10/28) - 7 AM (10/30)
> System: All Steam and Condensate Return
> Duration: 48 hours
> Reason:
> To re-insulate steam station in Room 48-002. It is very hot in this room
> - re-insulation will control the temperature considerably.
>
> Effect:
> Loss of all steam (high, medium, low pressure) and condensate return. This
> means there will be no hot domestic water (used in bathroom, kitchen, lab
> sink faucets and emergency showers) and hot lab process water (used for
> some lab equipment) during the shutdown period..
>
>