[52558] in Hotline Meeting
Bldg. 26 - 10/25 - All Water Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 25 10:27:08 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451105522@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@mit.edu>,
"'b-zone@mit.edu'"
<b-zone@mit.edu>,
"'cust-coach@mit.edu'" <cust-coach@mit.edu>,
"'dudley@mit.edu'" <dudley@mit.edu>,
"'gfp170@rle.mit.edu'"
<gfp170@rle.mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>,
"'ljtrudel@mit.edu'" <ljtrudel@mit.edu>, "'lsc@mit.edu'" <lsc@mit.edu>,
"'mhankin@mit.edu'" <mhankin@mit.edu>,
"'nsteele@mit.edu'"
<nsteele@mit.edu>,
"'radams@mit.edu'" <radams@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
"'rpc@mit.edu'"
<rpc@mit.edu>
Date: Wed, 25 Oct 2000 10:23:51 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; b-zone@mit.edu; cust-coach@mit.edu; dudley@mit.edu;
> gfp170@rle.mit.edu; kates@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; radams@mit.edu; safety@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; rpc@mit.edu
> Subject: Bldg. 26 - 10/25 - All Water Emergency Shutdown
>
>
The following All Water Emergency shutdown for Bldg. 26 for today,
Wednesday, 10/25 is for your information. If you have any question about
this, please contact Mr. Jack Allen at 3-6352.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: 26
> Date: 10/25/00
> Day: Wednesday
> Time: 11:30 AM - 12:30 PM
> System: All Water - both domestic and lab process
> Duration: 1 hour
> Reason:
> Relocate manhole at STATA Center site.
>
> Effect:
> Loss of all water (both domestic and lab process hot and cold). This means
> that no toilets, bathroom, kitchen, lab sink faucets, drinking fountains
> or emergency showers will be operational during this 1-hour shutdown
> period.
>
>