Bldgs. NW61, NW62 and N52 - 10/24 - Emergency Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 24 13:58:23 2000
Message-Id: <82F0D564C5ADD31180EF00508B55645110551B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'kcn@mit.edu'" <kcn@MIT.EDU>, "'mwhelan@mit.edu'" <mwhelan@MIT.EDU>,
"'jbutts@mit.edu'" <jbutts@MIT.EDU>,
"'nmagnuso@mit.edu'"
<nmagnuso@MIT.EDU>,
"'arhodes@mit.edu'" <arhodes@MIT.EDU>,
"'d-zone@mit.edu'" <d-zone@MIT.EDU>,
"'dianan@mit.edu'" <dianan@MIT.EDU>,
"'elayne@mit.edu'" <elayne@MIT.EDU>,
"'hdebaun@mit.edu'"
<hdebaun@MIT.EDU>,
"'honda@mit.edu'" <honda@MIT.EDU>, "'menos@mit.edu'"
<menos@MIT.EDU>,
"'mleen@mit.edu'" <mleen@MIT.EDU>, "'ronnc@MIT.EDU'"
<ronnc@MIT.EDU>,
"'sabenton@mit.edu'" <sabenton@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cperry@mit.edu'"
<cperry@MIT.EDU>,
"'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
Paul Stordy
<PStordy@PLANT.MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
"'lgross@mit.edu'"
<lgross@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Tue, 24 Oct 2000 13:54:59 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: kcn@mit.edu; mwhelan@mit.edu; jbutts@mit.edu; nmagnuso@mit.edu;
> arhodes@mit.edu; d-zone@mit.edu; dianan@mit.edu; elayne@mit.edu;
> hdebaun@mit.edu; honda@mit.edu; menos@mit.edu; mleen@mit.edu;
> ronnc@MIT.EDU; sabenton@mit.edu; dcarlson@mit.edu; cperry@mit.edu;
> pbaratta@mit.edu; mmahoney@mit.edu; Paul Stordy; D-Zone; lgross@mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldgs. NW61, NW62 and N52 - 10/24 - Emergency Power Shutdown
>
>
The following emergency power shutdown for the buildings listed above is for
your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: NW61, NW62 and N52
> Date: 10/24/00
> Day: Tuesday
> Time: 1 PM - unknown
> System: Electrical Power
> Duration: unknown
> Reason:
> Power Main break on east side of Massachusetts Avenue - Cambridge Electric
> working on this now.
>
> Effect:
> Loss of building power, computers, lighting (except emergency power),
> elevators, telephones int he above listed buildings.
>
>