[52452] in Hotline Meeting
Bldg. 35 - 10/21 - Rescheduled Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 18 09:58:25 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564511054D3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'b-zone@mit.edu'" <b-zone@MIT.Edu>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.Edu>,
"'emcmill@mit.edu'" <emcmill@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'gerwent@mit.edu'"
<gerwent@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'stiffler@mit.edu'" <stiffler@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'vclark@mit.edu'" <vclark@MIT.Edu>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
"'mmoreira@plant.mit.edu'"
<mmoreira@PLANT.MIT.EDU>
Date: Wed, 18 Oct 2000 09:55:22 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: b-zone@mit.edu; cust-coach@mit.edu; emcmill@mit.edu;
> gallant@mit.edu; gerwent@mit.edu; schedule@mit.edu; stiffler@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; vclark@mit.edu; James Sullivan;
> mmoreira@plant.mit.edu
> Subject: Bldg. 35 - 10/21 - Rescheduled Building Power Shutdown
> Request
>
>
The following rescheduled building power shutdown request for Bldg. 35 now
on Saturday, October 21 AM is again for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thank you again for your time.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35
> Date: 10/21/00
> Day: Saturday
> Time: 6 AM - 9 AM
> System: Building Power
> Duration: 3 hours
> Reason:
> Explore existing switch gear prior to making crossover power to Building
> 33.
>
> Effect:
> Loss of building power, elevators, computers, lighting (except for
> emergency lighting in stairs), Air: supply ventilation, supply cooling and
> supply heating during the 3-hour shutdown period.
>
>