[52433] in Hotline Meeting
Bldg. 36- 236 - 10/18 Revised Exhaust-General Air Shutdown Reques
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 17 13:36:47 2000
Message-Id: <82F0D564C5ADD31180EF00508B5564511054CC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'b-zone@mit.edu'" <b-zone@MIT.EDU>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.EDU>,
"'gfp170@rle.mit.edu'" <gfp170@rle.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'agallant@mit.edu'" <agallant@MIT.EDU>
Date: Tue, 17 Oct 2000 13:33:40 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: b-zone@mit.edu; cust-coach@mit.edu; gfp170@rle.mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; agallant@mit.edu
> Subject: Bldg. 36- 236 - 10/18 Revised Exhaust-General Air Shutdown
> Request
>
>
The following revised exhaust general air shutdown request for Bldg. 36 (now
for room 236 - not Basement) is again for your review and comment. Would
you please let me know whether this has your approval or does not.
Thank you again,
Andrea Nichols
Operations Center
8-7782
> Status: Normal
> Building: 36 - 236
> Date: 10/18/00
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Exhaust-General Air
> Duration: 8 hours
> Reason:
> Noise on 7th floor/replacement of bearings, belts, etc. (Fan #702035)
>
> Effect:
> Loss of general exhaust fan (PM#702035) which affects 36-236 only during
> the shutdown period.
>
>