Building 31 on 10-18 Hot and Cold potable and non-potable water

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Oct 17 08:06:19 2000

Message-ID: <82F0D564C5ADD31180EF00508B5564519F8AD6@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Paul DeSantis <pdesanti@PLANT.MIT.EDU>, ameswf@mit.edu,
        B-Zone
	 <B-Zone@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        gallant@mit.edu, rcf@space.mit.edu, schedule@mit.edu, thane@mit.edu,
        schedule@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 17 Oct 2000 08:03:13 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Paul DeSantis; ameswf@mit.edu; B-Zone; Cust-Coach; gallant@mit.edu;
> rcf@space.mit.edu; schedule@mit.edu; thane@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 31 on 10-18 Hot and Cold potable and non-potable
> water
> 
> 
The following shutdown request for buiding 31 on 10-18-00.  Please let me
know if this does or does not meet with your approval.

Thank you 
Dawn Simonelli
Repair and Maintenance	
2-1599

> Status: Normal
> Building: 31
> Date: 10/18/00
> Day: Wednesday
> Time: 3:00 pm to 9:00 pm
> System: Hot and cold potable and non potable water
> Duration: 6 hours
> Reason: 
> Confirmation of the complete seperation of potable and non-potable water
> through back flow prevention devices.
> 
> Effect: 
> There wil be no potable or non potable hot or cold water.
> 
> 