[52368] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. 9 and 35 - 10/17 PM - 10/18 AM, 10/18 PM - 10/19 AM - Supp

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 13 09:43:31 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511054A4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'emcmill@mit.edu'" <emcmill@MIT.EDU>,
        "'gerwent@mit.edu'"
	 <gerwent@MIT.EDU>,
        "'stiffler@mit.edu'" <stiffler@MIT.EDU>,
        "'gallant@mit.edu'" <gallant@MIT.EDU>,
        "'jobrien@mit.edu'"
	 <jobrien@MIT.EDU>,
        "'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'" <ndk@MIT.EDU>, "'randy@mit.edu'" <randy@MIT.EDU>,
        "'sexton@mit.edu'" <sexton@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
        "'westlund@mit.edu'" <westlund@MIT.EDU>,
        "'edorsch@mit.edu'"
	 <edorsch@MIT.EDU>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.EDU>,
        "'src@mit.edu'" <src@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        B-Zone
	 <B-Zone@MIT.EDU>
Date: Fri, 13 Oct 2000 09:40:28 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	emcmill@mit.edu; gerwent@mit.edu; stiffler@mit.edu; gallant@mit.edu;
> jobrien@mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu; randy@mit.edu;
> sexton@mit.edu; src@mit.edu; westlund@mit.edu; edorsch@mit.edu;
> sdl-adm-lib@mit.edu; src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; B-Zone
> Subject: 	Bldgs. 9 and 35 - 10/17 PM - 10/18 AM, 10/18 PM - 10/19 AM -
> Supply Ventilation Shutdown Request
> 
> 
The following shutdown request for Bldgs. 9 and 35 (which also affects
building 33) on Tuesday, 10/17 PM to Wednesday, 10/18 AM is for your
information and comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 9 & 35 (also 33)
> Date: 10/17/19
> Day: Tuesday
> Time: 6 PM (10/17) - 7 AM (10/18); 6 PM (10/18) - 7 AM (10/19)
> System: supply ventilation
> Duration: 2 days
> Reason: 
> Install silkal flooring in Bldg. 33 (patch work damaged by construction.)
> 
> Effect: 
> Loss of supply ventilation (fresh air from outside) in Bldgs. 9 and 35 -
> all floors during the 2-night shutdown period.
> 
> 