9 all perimter rooms on 10-13-00

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Oct 11 09:51:39 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564519F85BC@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: kirky@ceci.mit.edu, pam@ceci.mit.edu, shutdowns@MIT.EDU,
        Schedules Office <schedules@MIT.EDU>
Cc: shutdown@plant.mit.edu
Date: Wed, 11 Oct 2000 09:48:51 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	kirky@ceci.mit.edu; pam@ceci.mit.edu; shutdowns@mit.edu; Schedules
> Office
> Cc: 	shutdown@plant.mit.edu
> Subject: 	9 all perimter rooms on 10-13-00
> 
> 
The following shutdown request is for Blgd 9 all perimeter rooms from the
3rd to the 5th floorson October 13th.   Please let me know if this does or
does not meet with your approval.

> Status: Critical
> Building: 9
> Date: 10/13/00
> Day: Friday
> Time: 7:00AM - 3:00 PM
> System: Perimeter heating 
> Duration: 8 hours
> Reason: 
> Replace valves on heating system.
> 
> Effect: 
> No heating hot water.  Perimeter heating will be off during the shutdown
> 
> 