Shutdown request for building 31 on OLctober 18 2000.
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Oct 11 08:51:21 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564519F859A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: capone@mit.edu, D-Zone <D-Zone@mit.edu>, eisen@mit.edu, flett@mit.edu,
lsc@mit.edu, mwf@mit.edu, pwalsh@mit.edu, rberlin@mit.edu,
sdimond@mit.edu, shutdowns@mit.edu, schedule@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 11 Oct 2000 08:48:31 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: capone@mit.edu; D-Zone; eisen@mit.edu; flett@mit.edu; lsc@mit.edu;
> mwf@mit.edu; pwalsh@mit.edu; rberlin@mit.edu; sdimond@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 31 on OLctober 18 2000.
>
>
The following shutdown request is for building 31 on October 18. This
includes all rooms with in the building 31 using hot and cold potable and
non potable water. Please let me know if this does or does not have your
apporval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Critical
> Building: 31
> Date: 10/18/00
> Day: Wednesday
> Time: 3:00 pm - 9:00 pm
> System: Hot and Cold Potable and Non-Potable Water
> Duration: 6 Hours
> Reason:
> The complete seperaton of potable and non potable water through backflow
> prevention devices.
>
>
> Effect:
> There will be no hot and cold domestic water and no hot or cold lab
> processed water.
>
>