Bldgs. W31 and W32 - 10/12-13 - Electrical Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 10 08:01:54 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451105466@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'clroyer@mit.edu'" <clroyer@MIT.EDU>,
        "'d-zone@mit.edu'"
	 <d-zone@MIT.EDU>,
        "'djmartin@mit.edu'" <djmartin@MIT.EDU>,
        "'jaheiney@mit.edu'" <jaheiney@MIT.EDU>,
        "'kenstone@mit.edu'"
	 <kenstone@MIT.EDU>,
        "'marionoc@mit.edu'" <marionoc@MIT.EDU>,
        "'pbarratta@mit.edu'" <pbarratta@MIT.EDU>,
        "'slett@mit.edu'"
	 <slett@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 10 Oct 2000 07:59:05 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	clroyer@mit.edu; d-zone@mit.edu; djmartin@mit.edu; jaheiney@mit.edu;
> kenstone@mit.edu; marionoc@mit.edu; pbarratta@mit.edu; slett@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. W31 and W32 - 10/12-13 - Electrical Power Shutdown
> Request
> 
> 
The following electrical power shutdown request for Bldgs. W31 and W32 on
Thursday, 10/12 and Friday, 10/13 is for your review and comment. Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872 

> Status: Normal
> Building: W31 and W32
> Date: 10/12/13
> Day: Thursday
> Time: 11 PM (10-12) - 7 AM (10-13)
> System: Electrical Power
> Duration: 8 hours
> Reason: 
> Hood in new power sources to electrical system.
> 
> Effect: 
> 
> 
> Loss of Power:  Bldg. power, computers, telephones, lighting,
> corridors-stairs; Air: supply ventilation, supply cooling, supply heating,
> fire alarm system; 
> Note: Campus Police Department will not be affected - they are on
> Emergency Power System.
> 
> 