[52260] in Hotline Meeting
FW: Street Paving & Asbestos Abatement
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 5 10:49:58 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451105444@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'tr6@mit.edu'" <tr6@MIT.EDU>, "'jdoucett@mit.edu'" <jdoucett@MIT.EDU>,
"'tdoyle@mit.edu'" <tdoyle@MIT.EDU>,
"'emcmill@mit.edu'"
<emcmill@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'safety@mit.edu'" <safety@MIT.EDU>,
"'rdavies@mit.edu'"
<rdavies@MIT.EDU>
Date: Thu, 5 Oct 2000 10:47:08 -0400
Mime-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
FYI.
Andrea Nichols
Operations Center
8-7872
----------
From: Vinny Clark [SMTP:VClark@PLANT.MIT.EDU]
<mailto:[SMTP:VClark@PLANT.MIT.EDU]>
Sent: Thursday, October 05, 2000 10:28 AM
To: Plant-All; 'stiffler@mit.edu'; 'gutowski@mit.edu'; 'sachs@mit.edu';
'gerwent@mit.edu'; 'jmk@mit.edu'; 'smethurs@mit.edu'; 'aa-bldg33@mit.edu';
'jmcd@mit.edu'
Subject: Street Paving & Asbestos Abatement
Street Paving;
* The street and sidewalk upgrades on the alley between buildings 35
and 37 has begun and will be completed 10/28/00. It consists of installing
new street and sidewalk paving. There will be noise and dust associated
with the work and water will be used to control dust.
Asbestos Abatement
* The elevator lobby zone between 33 & 35 will receive new vinyl tile
flooring. But the asbestos tiles on the 2nd, 3rd & 4th floors will have to
be removed, basement and 1st floors have been abated. The 2nd and 4th
floors will be abated beginning Friday, 10/13/00 and completed on Saturday
10/14/00 and the 3rd floor will begin on Friday, 10/20/00 and completed on
Saturday, 10/21/00. These areas will sealed off to allow for abatement and
access to these locations will not be available during the abatement.