Bldg. E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C - 1

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 4 13:18:34 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451105437@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cperry@mit.edu'"
	 <cperry@MIT.EDU>,
        "'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        Doug Boyer
	 <dboyer@PLANT.MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>
Date: Wed, 4 Oct 2000 13:15:51 -0400 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> mmahoney@mit.edu; Doug Boyer; cust-coach@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu;
> E-Zone
> Subject: 	Bldg. E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B,
> 342C - 10/5 Approved Shutdown Request 
> 
> 
The following approved shutdown request for Bldg. E25 - 335, 335B, 335C,
335A, 330, 342, 342A, 342B, 342C on Thursday, 10/5 is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872 

> Status: Normal
> Building:  E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C 
> Date: 10/5/00
> Day: Thursday
> Time: 5 AM - 7 AM
> System: Receptacles, computers, lighting
> Duration: 2 hours
> Reason: 
> Faulty main breaker needs to be replaced (Panel DPLA3F #6).
> 
> Effect: 
> Loss of building power, computers, lighting in corridors in/outside rooms
> E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C during the 2-hour
> shutdown period.
> 
> 