[52227] in Hotline Meeting
Bldg. 16 - 10/5 - Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 3 10:46:07 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451105423@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'a-zone@mit.edu'" <a-zone@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'bengel@mit.edu'" <bengel@MIT.EDU>,
"'carolr@mit.edu'" <carolr@MIT.EDU>,
"'cbates@mit.edu'" <cbates@MIT.EDU>,
"'cbutters@mit.edu'" <cbutters@MIT.EDU>,
"'childs@mit.edu'"
<childs@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
"'daczel@mit.edu'" <daczel@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
"'gibbhen@mit.edu'" <gibbhen@MIT.EDU>,
"'goodluck@mit.edu'"
<goodluck@MIT.EDU>,
"'inn@mit.edu'" <inn@MIT.EDU>, "'jmganno@mit.edu'"
<jmganno@MIT.EDU>,
"'kreposa@mit.edu'" <kreposa@MIT.EDU>,
"'lechtman@mit.edu'" <lechtman@MIT.EDU>,
"'mgray@mit.edu'"
<mgray@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdowney@mit.edu'" <sdowney@MIT.EDU>,
"'steve@hstbme.mit.edu'"
<steve@hstbme.mit.edu>,
"'trometer@mit.edu'" <trometer@MIT.EDU>,
"'wyckoff@mit.edu'" <wyckoff@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 3 Oct 2000 10:43:25 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: a-zone@mit.edu; shutdowns@mit.edu; bengel@mit.edu; carolr@mit.edu;
> cbates@mit.edu; cbutters@mit.edu; childs@mit.edu; cust-coach@mit.edu;
> daczel@mit.edu; frc@mit.edu; gibbhen@mit.edu; goodluck@mit.edu;
> inn@mit.edu; jmganno@mit.edu; kreposa@mit.edu; lechtman@mit.edu;
> mgray@mit.edu; schedule@mit.edu; sdowney@mit.edu; steve@hstbme.mit.edu;
> trometer@mit.edu; wyckoff@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 16 - 10/5 - Critical Shutdown Request
>
>
The following Critical shutdown request for Bldg. 16 on Thursday, 10/5 is
for your review and comment. Would you please let me know whether this does
or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 16
> Date: 10/5/00
> Day: Thursday
> Time: 7 AM - 3 PM
> System: Air Handlers 1 and 2
> Duration: 8 hours
> Reason:
> Install carbon filters to eliminate diesal fumes from construction.
>
> Effect:
> Some loss of supply ventilation, supply cooling and supply heating in
> Bldg. 16 since each Air Handler will be down one at a time and will serve
> as backup to the Air Handler that is operational.
>
>