[52164] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C - 1

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 29 13:25:43 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511053FE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cjbeal@mit.edu'" <cjbeal@MIT.EDU>, "'bengel@mit.edu'"
	 <bengel@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 29 Sep 2000 13:23:10 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	cjbeal@mit.edu; bengel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B,
> 342C - 10/5 - Shutdown Request
> 
> 
The following building power shutdown request for E25 - 335, 335B, 335C,
335A, 330, 342, 342A, 342B, 342C on Thursday, 10/5 is for your information
and comment.  Would you please let me know whether this does or does not
have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C -
> Date: 10/5/00
> Day: Thursday
> Time: 5 AM - 7 AM
> System: Bldg. power, computers, lighting/corridors/stairs
> Duration: 2 hours
> Reason: 
> Faulty main breaker must be replaced. - Panel DPL A3F #6.
> 
> Effect: 
> Loss of building power, computers, lighting in corridors in/outside rooms
> E25 - 335, 335B, 335C, 335A, 330, 342, 342A, 342B, 342C during the 2-hour
> shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post