Bldg. 9 - floors 2 thru 6 - 10/7-8 - Rescheduled Asbestos Removal

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 22 13:26:32 2000

Message-ID: <82F0D564C5ADD31180EF00508B556451105398@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cust-coach@mit.edu'" <cust-coach@mit.edu>,
        "'deedc@mit.edu'"
	 <deedc@mit.edu>,
        "'gallant@mit.edu'" <gallant@mit.edu>,
        "'jobrien@mit.edu'" <jobrien@mit.edu>,
        "'mlavalle@mitvma.mit.edu'"
	 <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'" <ndk@mit.edu>, "'randy@mit.edu'" <randy@mit.edu>,
        "'sexton@mit.edu'" <sexton@mit.edu>, "'src@mit.edu'" <src@mit.edu>,
        "'westlunc@mit.edu'" <westlunc@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 22 Sep 2000 13:24:10 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	cust-coach@mit.edu; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> mlavalle@mitvma.mit.edu; ndk@mit.edu; randy@mit.edu; sexton@mit.edu;
> src@mit.edu; westlunc@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 9 - floors 2 thru 6 - 10/7-8 - Rescheduled Asbestos
> Removal/Shutdown Notification
> 
> 
The following rescheduled asbestos removal notification and shutdown for
Bldg. 9 - floors 2 thru 6 is now for Saturday, 10/7 and Sunday, 10/8.  Would
you please let me know if these new dates meet with your approval or do not.

Thank you again for your time.

Andrea Nichols
Operations Center
8-7872
Op

> Status: Normal
> Building:  9 - floors 2 thru 6
> Date: 10/7/08
> Day: Saturday
> Time: 8 AM (10/7) - 8 PM (10/8)
> System: Air Handler 1/supply ventilation, supply cooling, supply heating
> Duration: 36 hours
> Reason: 
> Asbestos removal from coil access door in Mech. Room 0050.
> 
> Effect: 
> No access to 0050 during the asbestos removal period.  Loss of supply
> ventilation (fresh air from outside), supply cooling (cooling) and supply
> heating (not on yet) in Bldg. 9 floors 2 thru 6 during the shutdown
> period.
> 
> 