Bldg. 3 - Toilet exhaust , exhaust-laboratory and supply cooling/
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 15 11:11:30 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451105327@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mward@mit.edu'" <mward@mit.edu>, "'archall@mit.edu'"
<archall@mit.edu>,
"'andreab@mit.edu'" <andreab@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'cust-coach@mit.edu'"
<cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dory@mit.edu'" <dory@mit.edu>,
"'engler@mitvma.mit.edu'"
<engler@mitvma.mit.edu>,
"'fenner@mit.edu'" <fenner@mit.edu>,
"'gossard@mit.edu'" <gossard@mit.edu>, "'ikec@mit.edu'" <ikec@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'mamullow@mit.edu'"
<mamullow@mit.edu>,
"'ndk@mit.edu'" <ndk@mit.edu>,
"'pmccosco@mit.edu'"
<pmccosco@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdimond@mit.edu'" <sdimond@mit.edu>,
"'sexton@mit.edu'"
<sexton@mit.edu>,
"'tetaylor@mit.edu'" <tetaylor@mit.edu>,
"'vipinternal@mit.edu'" <vipinternal@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 15 Sep 2000 11:07:57 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: mward@mit.edu; archall@mit.edu; andreab@mit.edu; shutdowns@mit.edu;
> cust-coach@mit.edu; dfucillo@mit.edu; dory@mit.edu; engler@mitvma.mit.edu;
> fenner@mit.edu; gossard@mit.edu; ikec@mit.edu; jobrien@mit.edu;
> mamullow@mit.edu; ndk@mit.edu; pmccosco@mit.edu; schedule@mit.edu;
> sdimond@mit.edu; sexton@mit.edu; tetaylor@mit.edu; vipinternal@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 3 - Toilet exhaust , exhaust-laboratory and supply
> cooling/9/21 Shutdown Request
>
>
The following shutdown request for Bldg. 3 - Toilet Exhuast,
exhaust-laboratory and supply cooling air oin Thursday, 9/21 is for your
information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Operations Cente
8-7872
> Status: Normal
> Building: 3 - floors 1, 2, 3 and 4
> Date: 9/21/00
> Day: Thursday
> Time: 7 AM - 3 PM
> System: Supply cooling, exhaust-laboratory, exhaust-general and exhaust
> toilet air
> Duration: 8 hours
> Reason:
> Preventive maintenance work on the following hoods and locations:
> PM#717662 - Fan Exhaust Hood in room 259 (Exhaust laboratory air); #701353
> - Air Handler 4/Supply fan - 4th floor (supply cooling); #717646 General
> Exhaust Fan for rooms 401 and 402; #716892 - Air Handler 6/Supply Fan -
> supply cooling for rooms 412 and 402; #703398 - Fan Exhaust Hood (Exhaust
> Laboratory Air) in Room 159; #719672 - Exhaust-toilet air on floors 1, 2
> and 3; and #702421 - Fan Exhaust General Air for Trench; 068, 051 and
> 050.
>
> Effect:
> Loss of supply cooling, exhaust-laboratory, exhaust-general and
> exhaust-toilet air. Each unit will be down for approximately 1 hour
> while the other units will remain on.
>
>