[52005] in Hotline Meeting
Bldg. 3 - 9/19 - Critical Compressed Control/Lab Air/Cooling 9/19
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 15 09:26:39 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451105325@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'admitmr@mitvmc.mit.edu'" <admitmr@mitvmc.mit.edu>,
"'archall@mit.edu'" <archall@mit.edu>,
"'andreab@mit.edu'"
<andreab@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dory@mit.edu'" <dory@mit.edu>,
"'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
"'fenner@mit.edu'"
<fenner@mit.edu>,
"'gossard@mit.edu'" <gossard@mit.edu>, "'ikec@mit.edu'" <ikec@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'mamullow@mit.edu'" <mamullow@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>,
"'pmccosco@mit.edu'" <pmccosco@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'sdimond@mit.edu'" <sdimond@mit.edu>,
"'sexton@mit.edu'" <sexton@mit.edu>,
"'tetaylor@mit.edu'"
<tetaylor@mit.edu>,
"'vipinternal@mit.edu'" <vipinternal@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 15 Sep 2000 09:23:28 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: admitmr@mitvmc.mit.edu; archall@mit.edu; andreab@mit.edu;
> shutdowns@mit.edu; dfucillo@mit.edu; dory@mit.edu; engler@mitvma.mit.edu;
> fenner@mit.edu; gossard@mit.edu; ikec@mit.edu; jobrien@mit.edu;
> mamullow@mit.edu; ndk@mit.edu; pmccosco@mit.edu; schedule@mit.edu;
> sdimond@mit.edu; sexton@mit.edu; tetaylor@mit.edu; vipinternal@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 3 - 9/19 - Critical Compressed Control/Lab Air/Cooling
> 9/19 Shutdown Request
>
>
The following Critical shutdown request for Bldg. 3 on Tuesday, 9/19 is for
your review and comment. Would you please let me know whether this does or
does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 3
> Date: 9/19/00
> Day: Tuesday
> Time: 7:30 AM - 11:30 AM
> System: Compressed Control/lab air/supply cooling
> Duration: 4 hours
> Reason:
> Tie in central compressed air system.
>
> Effect:
> Loss of compressed control/lab air as well as supply cooling in building
> during the shutdown period.
>
>