[51715] in Hotline Meeting
Bldgs. 14, 50, 1, 2, 3, 4, 5, 6, 6A, 7, 7A, 8, 10, 62, 64, N9 and
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 16 14:53:08 2000
Message-Id: <82F0D564C5ADD31180EF00508B5564511051F4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cperry@mit.edu'"
<cperry@MIT.EDU>,
"'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
C-Zone <C-Zone@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
"'wpwohlfa@mit.edu'"
<wpwohlfa@MIT.EDU>,
"'mmoreira@plant.mit.edu'" <mmoreira@plant.mit.edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>,
Steven Gilligan
<sgilliga@PLANT.MIT.EDU>,
"'muddyjoec@hotmail.com'"
<muddyjoec@hotmail.com>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Wed, 16 Aug 2000 14:51:32 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> cust-coach@mit.edu; A-Zone; C-Zone; D-Zone; wpwohlfa@mit.edu;
> mmoreira@plant.mit.edu; Paul Stordy; Steven Gilligan;
> muddyjoec@hotmail.com
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu
> Subject: Bldgs. 14, 50, 1, 2, 3, 4, 5, 6, 6A, 7, 7A, 8, 10, 62, 64,
> N9 and N10 - 8/14 PM - 15 AM Approved Shutdown Request
>
>
The following approved Emergency Power shutdown for Buildings Bldgs. 14, 50,
1, 2, 3, 4, 5, 6, 6A, 7, 7A, 8, 10, 62, 64, and Normal Power shutdown for N9
and N10 on Thursday, 8/17 PM to Friday, 8/18 AM is for your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 14, 50, 1, 2, 3, 4, 5, 6, 6A, 7, 7A, 8, 10, 62, 64, N9 and N10
> Date: 8/17/18
> Day: Thursday
> Time: 6 PM (8/17) - 6 AM (8/18)
> System: Emergency Power/Normal Power (N9 and N10 only)
> Duration: 12 hours
> Reason:
> To install a high voltage sectionalizing switch in Bldg. 14 which will
> minimize future shutdowns.
>
> Effect:
> Loss of Emergency Power (building power, lighting in corridors/stairs and
> perhaps telephones for buildings 1 thru 10 with the exception of 6-018
> from 6 PM - 6:20 PM on 8/17 and sometime after midnight on 8/18 for an
> undesignated period of 20 minutes. Emergency power for buildings 14, 50,
> 62 and 64 from 6 PM on 8/17 to 6 AM on 8/18.
> If there is any equipment on emergency power such as computers, they will
> go down.
> Loss of Normal power in Buildings N9 and N10 with the exception of
> N10-201(elevators, computers, telephones(?), and lighting in corridors.
>
> There may be loss of power in the following buildings:
> Building 10 - elevators
> Building 10 - Main group telephones
> Building 3 - Main Condensate Pump
> Building 3 - Manhole Main Sump Pump
> Building 6 - Room 018 Freezer & Refrigerator (will have back-up
> emergency
> power)
> Building 7 - Control Power for Air Handlers
> Building 7A - Elevators - Rotch Library and Exhaust Fans (will definitely
> go down).
> Building 2 - A.T.C. Boxes for Air Conditioners and heat.
>
>
>