[51642] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 1 - 151 - and some outlets in 1-143 - 8/9 Revised Approved

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 8 12:00:13 2000

Message-ID: <82F0D564C5ADD31180EF00508B55645110516F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@mit.edu>,
        "'atravers@mit.edu'"
	 <atravers@mit.edu>,
        "'dcarlson@mit.edu'" <dcarlson@mit.edu>,
        "'cperry@mit.edu'" <cperry@mit.edu>,
        "'pbaratta@mit.edu'"
	 <pbaratta@mit.edu>,
        "'mmahoney@mit.edu'" <mmahoney@mit.edu>,
        "'jcollins@mit.edu'" <jcollins@mit.edu>, C-Zone <C-Zone@mit.edu>,
        Donald Sullivan <DSulliva@PLANT.MIT.EDU>
Cc: RM-2ndShift <rm-2ndshift@mit.edu>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Tue, 8 Aug 2000 11:59:01 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patdixon@mit.edu; atravers@mit.edu; dcarlson@mit.edu;
> cperry@mit.edu; pbaratta@mit.edu; mmahoney@mit.edu; jcollins@mit.edu;
> C-Zone; Donald Sullivan
> Cc: 	RM-2ndShift; shutdown@plant.mit.edu; rm-shutdown@mit.edu;
> shutdowns@mit.edu
> Subject: 	Bldg  1 - 151 - and some outlets in 1-143 - 8/9 Revised
> Approved Shutdown
> 
> 
The following rescheduled approved Electrical Panel shutdown in Bldg. 1 -
151 and some outlets in 1-143 now on Wednesday, 8/9 is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 1-151 & some outlets in 1-143
> Date: 8/9/00
> Day: Wednesday
> Time: 5 PM - 9 PM
> System: Electric Panel in 1-151
> Duration: 4 hours
> Reason: 
> 1 1/4" conduit in corridor 000CB needs to be relocated for new ductwork.
> 
> Effect: 
> Loss of all power in 1-151 (affects lights, AV/cabinets, projector, MOT
> screen, Air Handler unit and some outlets in 1-143
> 
> 