[51557] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown exstension for FCS 3 entire campus

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jul 27 14:35:17 2000

Message-ID: <82F0D564C5ADD31180EF00508B5564517A23A6@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: shutdowns@mit.edu, jmganno@mit.edu, mcgrath@MTL.mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 27 Jul 2000 14:34:26 -0400
MIME-Version: 1.0
Content-Type: text/plain

To: 	shutdowns@mit.edu; jmganno@mit.edu; mcgrath@MTL.mit.edu
Cc: 	shutdown@plant.mit.edu
Subject: 	Shutdown exstension for FCS 3 entire campus


The shutdown for FCS 3 is going to be ex	tended until 3:00 pm.

Thank you 
Dawn Simonelli
2-1599

Status: Normal
Building: Entire campus
Date: 7/27/00
Day: Thursday
Time: Until 3:00 PM
System: FCS 3
Duration: 1 hour extra
Reason: 
back up of data

Effect: 
no SPT monitoring



home help back first fref pref prev next nref lref last post