Re: Shutdwon reques for buildings W31 & W32 on
daemon@ATHENA.MIT.EDU (Sandy Lett)
Thu Jul 27 13:55:46 2000
Message-Id: <3.0.2.32.20000727135845.01942ac0@hesiod>
Date: Thu, 27 Jul 2000 13:58:45 -0400
To: Dawn Simonelli <dsimone@PLANT.MIT.EDU>, clroyer@MIT.EDU,
D-Zone <D-Zone@MIT.EDU>, djmartin@MIT.EDU, jaheiney@MIT.EDU,
shutdowns@MIT.EDU
From: Sandy Lett <slett@MIT.EDU>
Cc: shutdown@PLANT.MIT.EDU
In-Reply-To: <82F0D564C5ADD31180EF00508B5564517A2363@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Dawn,
Okay for shutdown. I have notified the Athletic Staff.
Sandy
At 12:52 PM 07/27/2000 -0400, Dawn Simonelli wrote:
>> To: clroyer@mit.edu; D-Zone; djmartin@mit.edu; jaheiney@mit.edu;
>> slett@mit.edu; shutdowns@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: Shutdwon reques for buildings W31 & W32 on
>>
>>
>The following shutdown request for buildings W31 & W32 on Sunday is awaiting
>your approval. If you could let me know if this does or does not meet your
>approval.
>
>Thank you
>Dawn Simonelli
>2-1599
>
>> Status: Normal
>> Building: W31 & W32
>> Date: 7/30/00
>> Day: Sunday
>> Time: 7 am (or as early as possible)
>> System: Electrical shutdown
>> Duration: 6 hours
>> Reason:
>> Work installing breaker for W32 / W31 renovations.
>>
>>
>> Effect:
>> No power to computers, lighting. No chilled water. No supply ventilation
>> or supply cooling.
>>
>>
>
**********************************************************************