[51551] in Hotline Meeting
Shutdown request for building 33 on 7/29
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jul 27 12:22:30 2000
Message-ID: <82F0D564C5ADD31180EF00508B5564517A2349@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, emcmill@MIT.Edu,
gallant@MIT.Edu, gerwent@MIT.Edu, schedule@MIT.Edu, stiffler@mit.ed,
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 27 Jul 2000 12:21:30 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; emcmill@mit.edu; gallant@mit.edu;
> gerwent@mit.edu; schedule@mit.edu; stiffler@mit.ed; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 33 on 7/29
>
>
The following shutdown request is for building 33 on Saturday 7-29-00.
Please let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 33
> Date: 7/29/00
> Day: Saturday
> Time: 7:00am - 3:00 pm
> System: Hot and cold domestic water
> Duration: 8 hours
> Reason:
> To remove riser to allow construction of Tel/Data rooms
>
> Effect:
> no hot and cold domestic water
>
>