[50978] in Hotline Meeting
Bldg. 37 - 6/7 to 6/16 - Critical Chilled Water and Fan Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 23 11:10:36 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104DC8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'b-zone@mit.edu'" <b-zone@MIT.EDU>,
"'benford@space.mit.edu'"
<benford@space.mit.edu>,
"'breslau@space.mit.edu'"
<breslau@space.mit.edu>,
"'cmo@space.mit.edu'" <cmo@space.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'gallant@mit.edu'"
<gallant@MIT.EDU>,
"'murphy@space.mit.edu'" <murphy@space.mit.edu>,
"'politano@mit.edu'" <politano@MIT.EDU>,
"'rcf@space.mit.edu'"
<rcf@space.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'wendell@mit.edu'" <wendell@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 23 May 2000 11:08:37 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: b-zone@mit.edu; benford@space.mit.edu; breslau@space.mit.edu;
> cmo@space.mit.edu; shutdowns@mit.edu; gallant@mit.edu;
> murphy@space.mit.edu; politano@mit.edu; rcf@space.mit.edu;
> schedule@mit.edu; wendell@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 37 - 6/7 to 6/16 - Critical Chilled Water and Fan
> Shutdown Request
>
>
The following Critical shutdown request for Bldg. 37 from Wednesday, 6/7
through Friday, 6/16 is for your review and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 37
> Date: 6/7/16
> Day: Wednesday
> Time: 7:30 AM (6/7) - 3:30 PM (6/16)
> System: Air Handler 1 - chilled water and fan
> Duration: 10 days
> Reason:
> Replace chilled water coils.
>
> Effect:
> Loss of chilled water (air conditioning), supply ventilation (air from
> outside), supply cooling and supply heating (from supply fans) in Bldg.
> 37 during the shutdown period..
>
>