[50899] in Hotline Meeting
Bldg. 13 - 5/17 - Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon May 15 14:55:57 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104D64@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rhasselt@mit.edu'" <rhasselt@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 15 May 2000 14:54:10 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: rhasselt@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - 5/17 - Critical Shutdown Request
>
>
The following Critical shutdown for Bldg. 13 on Wednesday, 5/17 is for your
review and comment. Would you please let me know whether this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 13
> Date: 5/17/00
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Air Handler 3 North and South Perimeter induction unit
> Duration: 8 hours
> Reason:
> Repair Chilled Water coils - PM#701702 in 13-0091 (Air Handler 3).
>
> Effect:
> Loss of supply ventilation and supply cooling in the entire building -
> perimeter areas only.
>
>