Bldg. 2 - 009, 001, 013, all rooms above on each floor- 5/22 - 6/

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 11 15:08:18 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104D3D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'akelsey@mit.edu'" <akelsey@MIT.EDU>,
        "'andreab@mit.edu'"
	 <andreab@MIT.EDU>,
        "'c-zone@mit.edu'" <c-zone@MIT.EDU>,
        "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'cust-coach@mit.edu'"
	 <cust-coach@MIT.EDU>,
        "'duggins@math.mit.edu'" <duggins@math.mit.edu>,
        "'mbj@mit.edu'" <mbj@MIT.EDU>, "'preacher@mit.edu'" <preacher@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'sdimond@mit.edu'"
	 <sdimond@MIT.EDU>,
        "'seyferth@mit.edu'" <seyferth@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 11 May 2000 15:06:34 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	akelsey@mit.edu; andreab@mit.edu; c-zone@mit.edu;
> capozzi@math.mit.edu; cust-coach@mit.edu; duggins@math.mit.edu;
> mbj@mit.edu; preacher@mit.edu; schedule@mit.edu; sdimond@mit.edu;
> seyferth@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 - 009, 001, 013, all rooms above on each floor- 5/22
> - 6/9 Rescheduled Shutdown Request
> 
> 
The following rescheduled shutdown request for Bldg. 2 - 009, 001 and 013 as
well as the rooms above on each floor now for Monday, 5/22 through Friday,
June 9 is again for your review and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thank you again for your time and I look forward to hearing from you.

Andrea Nichols
Operations Center
8-7872 

> Status: Normal
> Building: 2-009, 001, 013 & all rooms above on each floor
> Date: 5/22/00
> Day: Monday
> Time: 7:30 AM  - 230 PM 
> System: Low Pressure Steam/Condensate Return
> Duration: 7 hours each day
> Reason: 
> All existing radiator heat is demolished, repiped and capped.
> 
> Effect: 
> No heat in Bldg. 2 for 3 weeks (from 5/22/00 thru 6/9/00.)
> 
> 