[50862] in Hotline Meeting
Bldg. E19 - 5/17 - Hot and Cold Water Rescheduled Shutdown Reques
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 11 10:21:46 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104D36@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Coach <rm-coach@MIT.EDU>, RM-ElecCtl <rm-elecctl@MIT.EDU>,
RM-Fire-Prot-Team <rm-fire-prot-team@MIT.EDU>,
RM-HvacSys
<rm-hvacsys@MIT.EDU>, RM-PipeSys <rm-pipesys@MIT.EDU>,
RM-Stockroom
<RM-Stockroom@PLANT.MIT.EDU>,
RM-StrcPnt <rm-strcpnt@MIT.EDU>,
RM-Stockroom <RM-Stockroom@PLANT.MIT.EDU>,
RM-Support
<RM-Support@MIT.EDU>, RM-TechTeam <rm-techteam@MIT.EDU>,
RM-Utl
<rm-utl@MIT.EDU>, RM-TechTeam <rm-techteam@MIT.EDU>,
RM-Teams
<rm-teams@MIT.EDU>,
"Roger J. Cayer" <rjcayer@PLANT.MIT.EDU>,
"'dcairns@mit.edu'" <dcairns@MIT.EDU>,
"'dlking@mit.edu'"
<dlking@MIT.EDU>,
"'e-zone@mit.edu'" <e-zone@MIT.EDU>,
"'elsagt@mit.edu'" <elsagt@MIT.EDU>, "'esico@mit.edu'" <esico@MIT.EDU>,
"'hallisey@mit.edu'" <hallisey@MIT.EDU>,
"'honiker@mit.edu'"
<honiker@MIT.EDU>,
"'joanf@mit.edu'" <joanf@MIT.EDU>,
"'joconor@mit.edu'" <joconor@MIT.EDU>,
"'kelley@mit.edu'"
<kelley@MIT.EDU>,
"'kshooter@mit.edu'" <kshooter@MIT.EDU>,
"'lambert@mitvma.mit.edu'" <lambert@mitvma.mit.edu>,
"'mbowers@mit.edu'"
<mbowers@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'rschmidt@mit.edu'" <rschmidt@MIT.EDU>,
"'sfalconi@mit.edu'"
<sfalconi@MIT.EDU>,
"'tmeehan@mit.edu'" <tmeehan@MIT.EDU>,
"'wbarrett@mit.edu'" <wbarrett@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'lsanto@mit.edu'" <lsanto@MIT.EDU>, "'edie@mit.edu'" <edie@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
Stephen McHugh
<smchugh@PLANT.MIT.EDU>, E-Zone <E-Zone@MIT.EDU>
Date: Thu, 11 May 2000 10:20:00 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: RM-Coach; RM-ElecCtl; RM-Fire-Prot-Team; RM-HvacSys; RM-PipeSys;
> RM-Stockroom; RM-StrcPnt; RM-Stockroom; RM-Support; RM-TechTeam; RM-Utl;
> RM-TechTeam; RM-Teams; Roger J. Cayer; 'dcairns@mit.edu';
> 'dlking@mit.edu'; 'e-zone@mit.edu'; 'elsagt@mit.edu'; 'esico@mit.edu';
> 'hallisey@mit.edu'; 'honiker@mit.edu'; 'joanf@mit.edu'; 'joconor@mit.edu';
> 'kelley@mit.edu'; 'kshooter@mit.edu'; 'lambert@mitvma.mit.edu';
> 'mbowers@mit.edu'; 'opsnote@mit.edu'; 'rschmidt@mit.edu';
> 'sfalconi@mit.edu'; 'tmeehan@mit.edu'; 'wbarrett@mit.edu';
> 'shutdowns@mit.edu'; 'lsanto@mit.edu'; 'edie@mit.edu'
> Cc: shutdown@plant.mit.edu; Stephen McHugh; E-Zone
> Subject: Bldg. E19 - 5/17 - Hot and Cold Water Rescheduled Shutdown
> Request
>
>
The following revised shutdown request for Blg. E19 is now for Wednesday,
5/17. Would you please let me know if this new date and time are more
convenient for you.
Thank you again for your time.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E19
> Date: 5/17/00
> Day: Wednesday
> Time: 2:30 PM - 7:30 PM
> System: Hot and cold domestic water
> Duration: 4 hours
> Reason:
> Install check valves on hot water supply.
>
> Effect:
> Loss of hot and cold domestic water (no toilets, bathroom, kitchen faucets
> or drinking fountains will be operational during the shutdown period.
> There are lavatories available in Bldgs. E17 - All floors and E25 - floors
> 1, 2, 3 and 5.
>
>