[50848] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 8 - 010, 110, 114, 116, 212, 214, 236A, 314, 316B, 316C, 41

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 10 11:35:55 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104D2A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>
Date: Wed, 10 May 2000 11:34:21 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	shutdowns@mit.edu; schedule@mit.edu
> Cc: 	
> Subject: 	Bldg. 8 - 010, 110, 114, 116, 212, 214, 236A, 314, 316B,
> 316C, 410 and 410B - 5/16 - 18 Revised Shutdown
> 
> 
The following revised shutdown for Bldg. 8 - 010, 110, 114, 116, 212, 214,
236A, 314, 316B, 316C, 410 nd 410B should be for Tuesday, 5/16, Wednesday,
5/17 and Thursday, 5/18 rather than 5/9, 10 and 11.  I am sorry that was my
fault.

Would you be good enough to let me know again if this new date would be all
right with your or not.

Thank you for your patience and I look forward to hearing from you.

Andrea Nichols
Operations Center
8-7872


> Status: Normal
> Building: 8 - 010, 110, 114, 116, 212, 214, 236A, 314, 316B, 316C, 410 and
> 410B 
> Date: 5/16/18
> Day: Tuesday
> Time: 7 AM - 3 PM each day
> System: drains, sinks - standpipes
> Duration: 3 days
> Reason: 
> Replace cast iron pipes that are cracked.
> 
> Effect: 
> Loss of hot and cold domestic water and hot and cold lab process water
> (would affect dains in the above listed labs, rooms only).  Sinks that
> cannot be used will be posted. Drains and standpipes will not be able to
> be used at the time of the shutdown period.
> 
> 