Bldg. E19 - 2nd floor - 5/5 Electrical Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 2 08:25:27 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104CAF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'safety@mit.edu'" <safety@MIT.EDU>, "'joanf@mit.edu'" <joanf@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 2 May 2000 08:24:03 -0400 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	safety@mit.edu; joanf@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E19 - 2nd floor - 5/5 Electrical Shutdown Request
> 
> 
The following electrical shutdown request for Bldg. E19 - 2nd floor on
Friday, 5/5 is for your review and comment.  

Would you please let me know whether this does or does not meet with  your
approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E19 - 2nd flooor
> Date: 5/5/00
> Day: Friday
> Time: 7:30 AM - 8:30 AM
> System: Electrical
> Duration: 1 hour
> Reason: 
> Tie in new electrical panel.
> 
> Effect: 
> Loss of building power (general air) and corridor lighting during 1-hour
> shutdown period.
> 
> 