LOG # 171025

daemon@ATHENA.MIT.EDU (Louis A. Isgur)
Tue Apr 11 13:35:52 2000

Message-Id: <200004111733.NAA14012@killer.mit.edu>
To: hotline@MIT.EDU
Date: Tue, 11 Apr 2000 13:33:46 -0400
From: "Louis A. Isgur" <larugsi@MIT.EDU>


------- Forwarded Message

Received: from PACIFIC-CARRIER-ANNEX.MIT.EDU by po9.MIT.EDU (5.61/4.7) id AA06767; Tue, 11 Apr 00 11:41:22 EDT
Received: from PLANT.MIT.EDU by MIT.EDU with SMTP
	id AA26593; Tue, 11 Apr 00 11:42:52 EDT
Received: by PLANT.MIT.EDU with Internet Mail Service (5.5.2650.21)
	id <2FG3PCAJ>; Tue, 11 Apr 2000 11:40:20 -0400
Message-Id: <82F0D564C5ADD31180EF00508B55645111AFEB@PLANT.MIT.EDU>
From: William Wohlfarth <wpwohlfa@PLANT.MIT.EDU>
To: William Wohlfarth <wpwohlfa@PLANT.MIT.EDU>,
        'Jonathon Weiss'
	 <jweiss@MIT.EDU>
Cc: ops@MIT.EDU, network@MIT.EDU, hardserv@MIT.EDU
Subject: RE: FW: Bldgs. 17A, 31, 33, 35 and 37 - 4/20 PM - 4/21 AM Shutdow
	n Re quest (Normal Electrical Power) 
Date: Tue, 11 Apr 2000 11:40:19 -0400
Mime-Version: 1.0
X-Mailer: Internet Mail Service (5.5.2650.21)
Content-Type: text/plain

I've postponed the shutdown until June 8th/9th...

Bill

> ----------
> From: 	Jonathon Weiss[SMTP:jweiss@MIT.EDU]
> Sent: 	Monday, April 10, 2000 5:04 AM
> To: 	William Wohlfarth
> Cc: 	'jweiss@mit.edu'; ops@MIT.EDU; network@MIT.EDU; hardserv@MIT.EDU
> Subject: 	Re: FW: Bldgs. 17A, 31, 33, 35 and 37 - 4/20 PM - 4/21 AM
> Shutdown Re quest (Normal Electrical Power) 
> 
> 
> Hi Bill, Sorry it's taken so long to get back to you.
> 
> > I hear you, and maybe we can just pick it up on another power source..
> >
> > The problem with postponing is that the new Bldg 35/33 project will need
> to
> > cut their new substation into the same loop fairly soon (June), and the
> > utility expansion project and the utility relocation for Stata all
> affect
> > the 13.8kv power distribution loops and the same resources
> (June/July)...
> > 
> > I'm concerned that if we don't get moving...I'll miss the window. This
> > particular shutdown has been in the works (unoffically) for 2
> years...and I
> > need to do it twice , a few weeks apart. 
> > 
> > If I have to cancel again ..so be it...but is there a win/win way to get
> > this done and keep you guys going?
> 
> Well, there are two issues.  The first one is power/cooling for
> 37-322.  This the server room that I care about and it's quite
> possible that you can come up with alternate power for that room, I
> don't know what the options are.  The room only contains 10 computers
> or so, so the power/cooling requirements aren't even that large.  The
> second problem is the Athena cluster (37-312,318,332).  This is
> actually teh responsibilty of the Athena Cluster services group (Brian
> Murphy, Lou Isgur and others), but I'm sure they aren't going to want
> to close this room this late in the term, and I think it's will be a
> lot harder to find alternate power for this much stuff.  Final exams
> end on Friday 5/19.  If there is any way we can wait till then, we'd
> still need to deal with 37-322, but I think people will feel more
> comfortable about closing the cluster.  (You should talk this over
> with the people from the Athean Cluster Services group tho, as this is
> really their department.)  I also gather that this would make your
> schedule really tight, I don't know if it is too tight or not tho.
> 
> 	Jonathon
> 

------- End of Forwarded Message